How does the remodel process work?
Of course all of this depends on complexity, but for a basic remodel project, expect:
- Measure up (1-2 hours)
- As-built drawings (3-5 hours depending on the size and complexity of the house)
- 2-3 quick sketches (freehand) of different options, and approximately 3-5 meetings of revisions
- Draft 'hard line' of the final option (8-10 hours)
- Present drawings to builders for estimates (first speed bump)
- Modify as needed to fit project budget
- Engineering (approx. $100/hr., 10-15 hours)
- Prepare final bid set (10-15 hours)
- Resubmission to builder for bid
- Apply for permit
- Construction starts